The Illinois Department of Transportation announced Sept. 7 that it will not allow a federal decision on the proposed Amtrak Hiawatha project to move forward until community concerns “have been adequately considered and addressed,” according to a news release.
IDOT has formally pledged to weigh freight and passenger rail needs and impacts on regular vehicle and pedestrian traffic as part of an overall resolution, according to the release.
The Illinois and Wisconsin departments of transportation and the Federal Railroad Administration have proposed increasing service on the Amtrak Hiawatha line, which runs from Chicago and Milwaukee and stops in Glenview, from seven to 10 daily round trips, according to the project’s draft environmental assessment.
Officials and North Shore residents have expressed concern about the proposal to build either a 10,000-foot freight train holding track on the east side of the two existing Metra train tracks or an 11,000-foot freight train holding track on the west side of the existing tracks from Glenview to Northbrook.
To build the freight train holding track, a 20-foot retaining wall would need to be built to hold the rail bed, officials said. Building the retaining wall would mean the green space that provides a buffer between the nearby residential areas and the existing tracks would be cut down.
Two new single-track bridges would also have to be built, one of which would cross Shermer Road, officials said. Glenview residents and staff have raised concerns about the bridge because in 2012 a train derailed on the bridge above Shermer Road, killing a Glenview couple.
The study into what improvements are needed to increase service between Milwaukee and Chicago is being led by the Wisconsin Department of Transportation, with the participation of IDOT, the Canadian Pacific Railroad, Metra, Amtrak and the FRA, according to the IDOT news release.
MORE COVERAGE: Glenview directs $400,000 to fight against Amtrak Hiawatha project “
Glenview looks to state reps, governor’s office in fight against Amtrak Hiawatha project “
To avoid duplicating the work that’s been done so far, IDOT officials will work to provide analysis that addresses the questions and concerns that have been raised by residents and officials within the ongoing Environmental Assessment that is required to meet federal environmental regulations, according to the press release.
“Based on the feedback we received, it’s apparent more analysis and outreach are required before this project moves forward,” Illinois Transportation Secretary Randy Blankenhorn said in the release. “We will be asking our project team to perform that analysis and do the necessary outreach so the impacted communities are more involved in the decision-making process.”
The agencies say that expanding Hiawatha service will address near capacity and over capacity conditions on peak time trains, give passengers more train time options and address “inadequate service reliability” because of conflicts with freight and other passenger traffic in the corridor, according to the assessment.
“Ridership has been steadily increasing and there is growing demand for more public transportation options in the Milwaukee-Chicago corridor. The current service is limited in its ability to meet this demand,” Arun Rao, of the Wisconsion Department of Transportation previously said.
Village officials and residents are concerned that the additional round trips are scheduled before and after rush hour, which does not seem to address Amtrak’s concern about over crowding on Hiawatha trains during peak travel times, Jeff Brady, Director of Community Development, previously said. Residents and officials have said that Hiawatha trains appear mostly empty when they pass Glenview.
About two weeks after the draft environmental assessment was released, the Glenview Board of Trustees passed a resolution opposing the findings in the assessment. The village cited three concerns: the alleged need to increase Hiawatha service by three round trips, short-term solutions proposed to accommodate rail traffic and environmental impacts.
The Glenview resolution states that village officials prefer establishing a 30-mile freight bypass through the area.
In March, Glenview held a community forum about the proposed project where residents and village officials expressed concerns about coal dust, exhaust fumes, the effect on emergency response times and the potential for derailments or chemical spills if the project is approved as proposed.
Residents also created a community-led Citizens for Alliance to Control Train Impacts in Our Neighborhoods to raise awareness about the proposed holding track.
Trustees in May approved a $400,000 fund to oppose the project “due to both the need being unwarranted and the absence of data on its full environmental impact,” according to the village’s website. Of the $400,000, the board approved a contract for $160,000 with Transportation Economics & Management Systems Inc. to study the capacity of the rail lines, officials said.
Deputy Village Manager Don Owen said Monday that Transportation Economics & Management Systems Inc. should be completing its study within 30 days. Though he declined to comment on the specifics of the study since it is still in draft form, Owen said the firm has given village staff indication that there are “viable alternatives” to building the holding track.
Over the years, Glenview officials have asked for data and information about the impacts the freight trains would have on the village, Owen said. But project officials would tell village staff that the proposed project impacts Amtrak trains, he said.
“For several years now, this project team has said, ‘Well we’re not going to give you data. This is about Amtrak trains, it’s not about freight trains.’ Our point is, you’re planning on changing how freight trains are operating here in Glenview,” Owen said.
Glenview has been a long supporter of passenger trains, with two Metra stations in the village, but officials and residents have concerns about freight trains stopping for an unknown length of time in the village, Owen said.
Specifically, the concerns are about the possibility of a freight train stopping on West Lake Avenue, which would delay ambulances heading to and from the hospital, Owen said.
The village is pleased that IDOT is taking the time to study the freight impacts and consider alternatives, Owen said.
Glenview officials have spent time studying the rail corridor and believe there are “better alternatives” that would minimize the impact on the village, Glenview President Jim Patterson said in the IDOT press release.
“We are grateful to the administration for listening to our concerns and directing their teams to study these alternatives,” Patterson said in the release.
IDOT spokesman Guy Tridgell said in an email Monday it is unclear how the delay will impact the project timeline and that IDOT has not established a timeline for when concerns should be addressed.